Tailings Booster Pumping Station

Client: Evolution Mining Ltd

Project : Tailings Booster Pumping Station

Site : Lake Cowal Operations

Date : January 2020 – August 2020

Complete fabrication of 500mm PN20 discharge pipe spooling and 400mm PN16 intake pipe spooling, inclusive of scour tees, sweeping bends, reducers and Y junctions. Blackpoly successfully completed all mechanical and civil onsite installation of steel and HDPE pipe spooling and valves. During a scheduled outage, the existing piping infrastructure was excavated and removed and spools were installed to successfully commission the pumping station

A Truck Is Being Loaded With Pipes In A Construction Site — Blackpoly Pipelines in Orange, NSW
July 22, 2024
Client: BGC Construction
A Yellow Komatsu Excavator Is Working On A Pipe — Blackpoly Pipelines in Orange, NSW
July 22, 2024
Client: Clarke Energy
A Truck Is Being Lifted By A Crane On A Dirt Road — Blackpoly Pipelines in Orange, NSW
July 22, 2024
Client: Synergy Resource Management
A Large Semi Truck Is Carrying A Large Load Of Pipes — Blackpoly Pipelines in Orange, NSW
July 22, 2024
Client: Synergy Resource Management
A Man Is Digging In The Dirt Near A Body Of Water — Blackpoly Pipelines in Orange, NSW
July 22, 2024
Client: Newcrest Mining Ltd
A Truck Is Carrying A Yellow Excavator On A Dirt Road — Blackpoly Pipelines in Orange, NSW
July 22, 2024
Client: Monadelphous
A Row Of Construction Vehicles Are Parked On The Side Of A Dirt Road — Blackpoly Pipelines in Orange, NSW
July 22, 2024
Client: Evolution Mining Ltd
A Construction Site With A Lot Of Pipes And A Yellow Excavator — Blackpoly Pipelines in Orange, NSW
July 22, 2024
Client: Newcrest Mining Ltd
A Construction Site With Pipes And A Bridge In The Background — Blackpoly Pipelines in Orange, NSW
July 22, 2024
Client: Abergeldie Complex Infrastructure, Veolia Water
A Yellow Komatsu Excavator Is Working On A Dirt Road — Blackpoly Pipelines in Orange, NSW
July 22, 2024
Client: Aurelia Metals Ltd
More Posts