500mm PN20 Con2 Tailings Pipeline
Client: Newcrest Mining Ltd
Project : 500mm PN20 Con2 Tailings Pipeline
Site : Cadia Valley Operations
Date : November 2017 – March 2018
Blackpoly completed the removal of an existing 760 metre section of de rated DN450 tailings pipeline and installed a 500mm pn20 pipeline. There were several challenges involved within the project with live services around major excavation areas and live powerline easements along the pipeline route. The pipeline was successfully commissioned during a major shutdown outage to ensure the mining operation could continue to operate unaffected.