500mm PN20 Con2 Tailings Pipeline

Client: Newcrest Mining Ltd

Project : 500mm PN20 Con2 Tailings Pipeline

Site : Cadia Valley Operations

Date : November 2017 – March 2018

Blackpoly completed the removal of an existing 760 metre section of de rated DN450 tailings pipeline and installed a 500mm pn20 pipeline. There were several challenges involved within the project with live services around major excavation areas and live powerline easements along the pipeline route. The pipeline was successfully commissioned during a major shutdown outage to ensure the mining operation could continue to operate unaffected.

A Truck Is Being Loaded With Pipes In A Construction Site — Blackpoly Pipelines in Orange, NSW
July 22, 2024
Client: BGC Construction
A Yellow Komatsu Excavator Is Working On A Pipe — Blackpoly Pipelines in Orange, NSW
July 22, 2024
Client: Clarke Energy
A Truck Is Being Lifted By A Crane On A Dirt Road — Blackpoly Pipelines in Orange, NSW
July 22, 2024
Client: Synergy Resource Management
A Large Semi Truck Is Carrying A Large Load Of Pipes — Blackpoly Pipelines in Orange, NSW
July 22, 2024
Client: Synergy Resource Management
A Truck Is Carrying A Yellow Excavator On A Dirt Road — Blackpoly Pipelines in Orange, NSW
July 22, 2024
Client: Monadelphous
A Row Of Construction Vehicles Are Parked On The Side Of A Dirt Road — Blackpoly Pipelines in Orange, NSW
July 22, 2024
Client: Evolution Mining Ltd
A Construction Site With A Lot Of Pipes And A Yellow Excavator — Blackpoly Pipelines in Orange, NSW
July 22, 2024
Client: Newcrest Mining Ltd
A Construction Site With Pipes And A Bridge In The Background — Blackpoly Pipelines in Orange, NSW
July 22, 2024
Client: Abergeldie Complex Infrastructure, Veolia Water
A Yellow Komatsu Excavator Is Working On A Dirt Road — Blackpoly Pipelines in Orange, NSW
July 22, 2024
Client: Aurelia Metals Ltd
A Construction Site With A Lot Of Machinery And Pipes — Blackpoly Pipelines in Orange, NSW
July 22, 2024
Client: Evolution Mining Ltd
More Posts